Shifting of Water Pipelines of Kerala Water Authority

Shifting of water pipelines of Kerala Water Authority (KWA) is a major task both physically and financially, as the table below shows:

Sl.No Chainage Present Position Estimate (in lakhs) Amount released

KSTP-4, PALAKKAD SHORNUR ROAD

1 4.00 - 9.00 Pipe relaying work completed 33.00 20.70
2 9.70 - 14.8 Pipe supplied by KSTP, 95% work completed 21.50 4.33
3 21.00 - 27.50 Work completed on both sides 34.00 16.00
4 34.00 - 36.00 Pipe supplied by KSTP, 90% work completed 18.50 21.34
5 36.00 - 39.00 Pipe supplied by KSTP, 75% work completed 23.70 24.40
6 39.00 - 42.60 Work arranged 18.50
7 42.60 - 45.00 32.50 27.25

KSTP-4, THRISSUR - KUTTIPPURAM ROAD

1 19.50 - 20.24
10.00 7.05
2 20.40 - 23.50 KWA to submit revised estimate 28.00
3 23.50 - 29.40 Major KWA pipes, replacement cost 450.00 11.75
4 30.00 - 32.70 Work completed 23.50 11.75
Pipe supplied by KSTP, work in progress 3.05 1.55
5 34.50 - 39.60 Work in progress 50.00 19.00
6 39.60 - 41.00 Estimate to be submitted by KWA 10.00
7 41.00 - 41.30 Work completed 11.50 8.25
8 41.30 - 52.50 KWA to submit revised estimate 50.00

KSTP-3, MUVATTUPUZHA - THODUPUZHA ROAD

1 2.00 - 4.00 KWA estimate received 23.80
2 4.00 - 9.80 Pipe supplied by KSTP, work in progress 21.00 7.27
3 9.80 - 17.00 KWA to submit estimate 23.80
4 17.00 - 19.80 Work arranged 6.17 4.43

KSTP-3, MUVATTUPUZHA - ANGAMALI ROAD

1 208.00 - 215.20 Work to be arranged 71.74 9.27
2 215.20 - 227.00 Work completed 83.10 70.68
3 227.00 - 240.00 KWA to submit estimate 6.17

KSTP-1, TAIKKOD - KOTTARAKKARA - CHENGANNUR ROAD

1 25.00 - 33.00 Work directly assigned by KSTP and completed 70.00 50.00
2 33.00 - 39.60 KWA estimate received 32.00
3 44.90 - 48.30 KWA estimate received 25.80
4 48.30 - 52.70 KWA estimate received 15.12
5 53.40 - 54.60 KWA estimate received 4.65
6 54.60 - 56.00 KWA estimate received 10.45
7 56.00 - 61.90 KWA estimate received, 25% PVC pipes supplied 13.85 3.46
8 62.50 - 68.20 KWA estimate received, 25% PVC pipes supplied 10.57 2.64
9 68.40 - 72.20 KWA estimate received, 25% PVC pipes supplied 13.90 3.48
10 72.20 - 72.60 KWA estimate received 9.30
11 78.40 - 83.00 KWA estimate received, 25% PVC pipes supplied 10.25 2.56
12 85.50 - 89.00 KWA estimate received 36.50
13 92.00 - 112.00 KWA to submit estimate 70.00

KSTP-1, TAIKKOD - ALAPPUZHA - CHANGANASSERY ROAD

1 0.00 - 4.80 KWA to submit revised estimate 30.00 2.30