OBJECTIVES OF ENVIRONMENTAL MANAGEMENT PLAN (EMP)

The main aim of EMP is to ensure that various adverse impacts due to the project are minimised / mitigated or avoided and the positive impacts are enhanced.

During construction state, the following objectives are ensured:

  • implementation of mitigation measures by the Contractor
  • ensuring that provisions of the MORT&H specifications, Indian Road Congress (IRC) codes and mitigation measures proposed in the EMP are strictly adhered toand implemented by strengthening implementation mechanism

DETAILS OF ENVIRONMENTAL PARAMETERS BEING MONITORED FOR KSTP-1, KSTP-3 & KSTP-4

The following parameters of environmental significance are monitored to ensure compliance by the contractor during construction stage.  While an engineer from the contractor's side as well as PWD's field Division are designated as Environmental Officers to monitor these parameters, the Envronmental Engineer from the Project Management Team (PMT), Thiruvananthapuram makes frequent field trips to ensure compliance of the parameters.

In addition, the World Bank Environmental team, during their visits to the site verify compliance and give instructions for improvement, if necessary.

Sl.No Item Action to be taken by Contractor
  At Construction Camps
1 Silt traps To be provided
2 Drainage system Closed system to be provided.  Also, separate lines for drinking water and waste water
3 Disposal of waste water soak pits / oil interceptor to be provided
4 Solid waste compost pit to be provided
5 Drinking water  Ground water to be tested once in 6 months
6 First Aid facility  
7 Roads Dust suppression to be practiced if roads are not tarred
8 Fuel storage sumps to be provided
9 Garbage garbage bins to be provided
10 Waste from Hot Mix plant can be used to develop approach roads and camp roads
  Quarry and Crusher
1 Consents  from a) Mining and Geology b) Dept. of explosives and c) KSPCB for establishment and operation required  
2 Magazine plan to be complied with
  Traffic Management Plan
1 IRC: SP: 55 and IRC: 67 Safety measures and equipment to conform to the IRC norms
2 reflective equipments To be provided
3 Lights and hurricane lamps To be provided
4 Cones  To be provided
5 Treated shoulder To be provided
6 Water sprinkling To be provided
  General
3

DG sets

Noise control systems to be provided

4

Safety

Installation of safety equipment and operation of safety

5

Oil interceptor

To be provided for the workshop floor

6

Borrow area

Burrow Management Plan to be submitted and approved

9 Compliance Report to consents issued by various Govt. Departments Contractor to prepare compliance report to all the consents
10

Compliance Report to World Bank Mission site observations

Contractor to prepare compliance report